500kV circuit-3 power transmission project must be completed by Sept. 2: PM

August 13,ket qua bong da truc 2024 - 20:01 Your browser does not support the audio element. The remaining works are mostly in the central provinces of Nghệ An and Hà Tĩnh, which are expected to be finished by August 18.
Prime Minister Phạm Minh Chính delivers a speech at a meeting on the implementation of the the 500kV circuit-3 power transmission line project on Tuesday. — VNA/VNS Photo

HÀ NỘI — Prime Minister Phạm Minh Chính has requested ministries, sectors, agencies, and localities to shorten timelines to complete the 500kV circuit-3 power transmission line project by September 2 to celebrate the 79th anniversary of the National Day.

Chairing a meeting on the implementation of the project on Tuesday, the fifth held in the past seven months, the PM ordered the mobilisation of human resources and equipment to ensure the progress, safety, and quality of the remaining workload, while conducting a trial run on parts of the system towards the whole project.

The project, running from Quảng Trạch in the central province of Quảng Bình to Phố Nối in the northern province of Hưng Yên, has a total length of about 519km and an investment of VNĐ22 trillion (US$875.62 million), with four component projects crossing nine provinces. Its construction started in January 2024.

To date, site clearance for 100 per cent of pile foundation locations and route corridors has been completed, along with pole casting at 100 per cent of locations, the erection of 1,159 out of 1,177 poles, and the construction and operation of the Nam Định 1-Thanh Hoá Power Plant sub-project.

The remaining works are mostly in the central provinces of Nghệ An and Hà Tĩnh, which are expected to be finished by August 18.

Pointing out difficulties facing the project, especially those from weather conditions and tough terrain, the PM requested contractors and workers to overcome all difficulties and maintain continuous work to ensure the project is completed on time.

He assigned detailed tasks to particular ministries, sectors, and localities, and directed all stakeholders to coordinate closely together to complete their missions.

The Government leader also asked localities to remain cognizant of environmental protection and resettlement for affected communities. — VNS

(责任编辑:Cúp C2)

相关内容
  • Thời tiết Miền Bắc và Trung Bộ vào đợt mưa lớn kéo dài
  • Hôm nay nắng nóng tăng lên 38
  • Bầu ông Nguyễn Thiện Nhân và bà Nguyễn Thị Kim Ngân vào Bộ Chính trị
  • Bộ trưởng Bộ Nội vụ: Quan phường còn yếu kém
  • Quận Hoàn Kiếm và 176 xã của Hà Nội thuộc diện phải sáp nhập
  • Vụ thịt ngựa giả bò: Người tiêu dùng mất lòng tin
  • Quảng Bình Lai dắt tàu cá cùng 4 ngư dân vào bờ an toàn
  • Phát hiện cá thể gấu quý hiếm nặng khoảng 150kg ở Quảng Trị
推荐内容
  • Lễ hội chọi trâu Đồ Sơn 2023 chỉ người có vé mời mới được vào sân
  • Phó Thủ tướng nói về việc nuôi lợn ở Hà Nam
  • DN sản xuất thanh nhựa “chết mòn” vì hàng nhập ngoại
  • Có bằng tốt nghiệp trung cấp, CĐ là được thi liên thông
  • Vietnam Airlines triển khai dịch vụ check
  • Quy định nổ súng còn sơ sài gây nghi ngại